Construction updates

Rio Grande Campus construction update: April 2021

Posted on Thu, 04/22/2021 - 2:29pm

Rio Grande Campus RenovationsBy Paul Mason, Rio Grande Renovations Project Manager The original project is now substantially complete as of March 1, 2021. We have performed several architectural interior and exterior punch list inspections to assess...

Continue reading


Rio Grande Campus construction update: March 2021

Posted on Thu, 03/11/2021 - 12:59pm

Rio Grande Campus RenovationsBy Paul Mason, Rio Grande Renovations Project Manager Austin Community College District's (ACC) Rio Grande Campus received a temporary certificate of occupancy for the building on February 11. We moved furniture and...

Continue reading


Rio Grand Campus hallway

Construction updates at Highland and Rio Grande: January/February 2021

Posted on Thu, 02/11/2021 - 12:54pm

Rio Grande Campus RenovationsBy Paul Mason, Rio Grande Renovations Project Manager RGC 1000 is quickly nearing completion. However, the college experienced a minor delay of a couple of weeks due to the impacts of a COVID-related shutdown that...

Continue reading


Construction updates at Highland and Rio Grande: November 2020

Posted on Thu, 12/03/2020 - 9:09am

Rio Grande Campus RenovationsBy Paul Mason, Rio Grande Renovations Project Manager Over the last month, we've made a good bit of progress toward completing this project. We are only two months from substantial completion! Inside the building, on...

Continue reading


Construction updates at Highland and Rio Grande: October 2020

Posted on Thu, 10/22/2020 - 11:00am

Rio Grande Campus RenovationsBy Paul Mason, Rio Grande Renovations Project Manager The project is entering the home stretch! We are about three months out from substantial completion. The interiors are really starting to come together. Final...

Continue reading


Construction updates at Highland and Rio Grande: July/August 2020

Posted on Thu, 08/27/2020 - 9:24am

RIO GRANDE CAMPUS RENOVATIONSBy Paul Mason, Rio Grande Renovations Project Manager Tremendous progress has been made over the past month. The two elevators are being installed. Decorative hand railing systems are being installed in the interior...

Continue reading


Construction updates at Highland and Rio Grande: May/June 2020

Posted on Thu, 07/30/2020 - 11:49am

The Highland Campus South Parking Garage hit another milestone this summer. Construction crews added the college's name to the external-facing wall, which is visible from Interstate 35, Highway 290, and areas to the east and southeast of the campus...

Continue reading